Four-Input Quote Readiness Gate
Four things decide whether a low-volume enquiry is ready for an engineered quotation or still needs clarification. Answer honestly—the point is to find the missing input before the commercial scope is fixed.
Gate 1 · Geometry
blocks programmingWhat can you send today?
Gap: without a dimensioned drawing nobody knows which features are critical, so the quote either guesses high or stalls on questions.
Gate 2 · Material
blocks procurementHow is the material specified?
Gap: a grade without a standard cannot be bought against a mill certificate, and certified stock has its own lead time.
Gate 3 · Tolerance
drives priceWhich dimensions actually have to be tight?
Gap: tightening every dimension instead of the sealing and mating faces is one of the most expensive habits in procurement.
Gate 4 · Documentation
blocks acceptanceWhat paperwork has to arrive with the parts?
Gap: 3.1 is signed by the manufacturer’s own independent inspection function; 3.2 needs a third-party countersignature and extra calendar time. Deciding late reopens the quote.
Readiness
Answer the four gates above to see where your enquiry stands.
What to fix first
Nothing you enter is stored or transmitted; the check runs entirely in your browser. A partial enquiry is still welcome — this tool exists so you know which answer will come back as a question.